TVA-417
780 MW generation in Muhlenberg, KY · In queue since February 2020 · Proposed COD October 2022
780 MW
Capacity
1
Components
Gas
6y 3m
In Queue
IA Executed
IA Status
COD target: 2022
Total Duration
2y 8m
Schedule
44 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2022-10-01
TVA-417 is a proposed 780 MW gas-fired generation project located in Muhlenberg County, Kentucky. The project, under development by the Tennessee Valley Authority (TVA), is interconnected to the Paradise 500-kV Station. It entered the TVA interconnection queue on February 10, 2020, and has a proposed commercial operation date of October 1, 2022. The project's interconnection agreement (IA) has been executed.
The proposed project consists of 780 MW of gas-fired capacity. It is currently listed as active in the TVA interconnection queue.
Generated from interconnection queue and public data sources
State
KY
County
Muhlenberg
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
Paradise 500-kV Station
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- TVA
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TVA-417