TVA-420
66 MW generation in Lawrence, AL · In queue since March 2020 · Proposed COD October 2024
66 MW
Capacity
1
Components
Solar
6y 2m
In Queue
Facility Study
IA Status
COD target: 2024
Total Duration
4y 7m
Schedule
19 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-10-15
The TVA-420 development project is a proposed 66 MW solar generation facility located in Lawrence County, Alabama. The project is listed in the Tennessee Valley Authority (TVA) interconnection queue with an entry date of March 25, 2020. Its proposed commercial operation date is October 15, 2024.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Colbert FP - Wheeler HP 161-kV TL.
Generated from interconnection queue and public data sources
State
AL
County
Lawrence
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
Colbert FP - Wheeler HP 161-kV TL
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.