Project TVA-433 — Project Summary

Queue ID
TVA-433
Capacity
100 MW
Technology
Battery
Status
active
Location
Clay, MS
Region
Southeast
Developer
IA Status
IA Executed

TVA-433

TVA-433BetaActiveBatteryTVALBNL

100 MW storage in Clay, MS · In queue since May 2020 · Proposed COD December 2028

100 MW

Capacity

1

Components

Battery

6 years

In Queue

IA Executed

IA Status

COD target: 2028

Interconnection

Total Duration

8y 7m

Construction75%
Queue EntryMay 15, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2028-12-14

About

TVA-433 is a proposed 100 MW battery storage project located in Clay County, Mississippi. The project, developed by the Tennessee Valley Authority (TVA), entered the TVA interconnection queue on May 15, 2020, and has a proposed commercial operation date of December 14, 2028. The interconnection agreement for the project has been executed.

The project will interconnect at the Clay 161-kV Substation. Recent news coverage has discussed the development project.

Generated from interconnection queue and public data sources

Project Details

State

MS

County

Clay

Grid Region

Southeast

Market

Developer

Utility

Tennessee Valley Authority

Entity

TVA

Service Type

Point of Interconnection

Clay 161-kV Substation

Data Source

LBNL

Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
Southern Company
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project TVA-433