TVA-446
127 MW generation in Lowndes, MS · In queue since July 2020 · Proposed COD March 2028
127 MW
Capacity
1
Components
Solar
5y 10m
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
7y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-03-06
TVA-446 is a proposed solar generation project with a total capacity of 127 MW, located in Lowndes County, Mississippi. The project is listed in the Tennessee Valley Authority (TVA) interconnection queue, with an entry date of July 1, 2020. The proposed commercial operation date is March 6, 2028. The point of interconnection is the Lowndes, MS 500-kV Substation.
The project's interconnection agreement has been executed. The developer is listed as TVA. Recent news coverage indicates interest in this project.
Generated from interconnection queue and public data sources
State
MS
County
Lowndes
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
Lowndes, MS 500-kV Substation
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TVA-446