TVA-466
200 MW generation in Clay, MS · In queue since February 2021 · Proposed COD June 2028
200 MW
Capacity
1
Components
Solar
5y 3m
In Queue
IA Executed
IA Status
COD target: 2028
Total Duration
7y 4m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-06-12
TVA-466 is a proposed 200 MW solar generation project located in Clay County, Mississippi. The project is listed in the Tennessee Valley Authority (TVA) interconnection queue with an entry date of February 8, 2021. The proposed commercial operation date is June 12, 2028, and the Interconnection Agreement (IA) has been executed.
The project, under the queue ID TVA-466, is being developed within the TVA service area and will interconnect at the West Point, MS 500-kV Substation (161-kV). The project has appeared in recent news coverage regarding TVA's renewable energy procurement plans.
Generated from interconnection queue and public data sources
State
MS
County
Clay
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
West Point, MS 500-kV Substation (161-kV)
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.