TVA-477
200 MW hybrid in Hardeman, TN · In queue since June 2021 · Proposed COD August 2029
200 MW
Capacity
1
Components
Solar
4y 11m
In Queue
IA Executed
IA Status
COD target: 2029
Total Duration
8y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2029-08-07
TVA-477 is a proposed 200 MW hybrid solar and battery project located in Hardeman County, Tennessee. The development project, consisting of 200 MW of solar power, is in the Tennessee Valley Authority (TVA) interconnection queue with an entry date of June 8, 2021. The proposed commercial operation date is August 7, 2029. The project's point of interconnection is the Selmer - Bolivar 161-kV TL Cordova - Hickory Valley No 2 161-kV TL.
The interconnection agreement for TVA-477 has been executed. The project has appeared in recent news coverage regarding TVA's generation portfolio.
Generated from interconnection queue and public data sources
State
TN
County
Hardeman
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
Selmer - Bolivar 161-kV TL Cordova - Hickory Valley No 2 161-kV TL
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- TVA
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TVA-477