TVA-485
130 MW hybrid in Bedford, TN · In queue since October 2021 · Proposed COD October 2028
130 MW
Capacity
1
Components
Solar
4y 7m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
7 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-20
TVA-485 is a proposed 130 MW hybrid solar and battery project located in Bedford County, Tennessee. The development project, consisting of 130 MW of solar power, is in the Tennessee Valley Authority (TVA) interconnection queue.
The project entered the queue on October 25, 2021, and has a proposed commercial operation date of October 20, 2028. Its interconnection agreement status is currently in the Facility Study phase. The point of interconnection is the Kedron Rd SW STA - Unionville SW STA 161- kV TL.
Generated from interconnection queue and public data sources
State
TN
County
Bedford
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
Kedron Rd SW STA - Unionville SW STA 161- kV TL
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- TVA
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.