TVA-503
70 MW generation in Gibson, TN · In queue since June 2022 · Proposed COD November 2024
70 MW
Capacity
1
Components
Solar
3y 11m
In Queue
Facility Study
IA Status
COD target: 2024
Total Duration
2y 5m
Schedule
18 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-11-08
TVA-503 is a proposed 70 MW solar generation project located in Gibson County, Tennessee. The project is being developed within the Tennessee Valley Authority (TVA) balancing authority area. It entered the TVA interconnection queue on June 20, 2022, and has a proposed commercial operation date of November 8, 2024. Its interconnection status is currently in the Facility Study phase.
The proposed project consists of 70 MW of solar photovoltaic generation. The point of interconnection is the Weakley - Dyersburg No1 161-kV TL.
Generated from interconnection queue and public data sources
State
TN
County
Gibson
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
Weakley - Dyersburg No1 161-kV TL
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- TVA
- Hub Confidence
- UNKNOWN