TVA-515
67 MW generation in Haywood, TN · In queue since August 2022 · Proposed COD September 2025
67 MW
Capacity
1
Components
Solar
3y 9m
In Queue
Facility Study
IA Status
COD target: 2025
Total Duration
3y 1m
Schedule
8 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-09-12
TVA-515 is a proposed 67 MW solar generation project located in Haywood County, Tennessee. The project is listed in the Tennessee Valley Authority (TVA) interconnection queue with an entry date of August 25, 2022. The proposed commercial operation date is September 12, 2025.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Covington - Alamo 161-kV transmission line. The project has appeared in recent news.
Generated from interconnection queue and public data sources
State
TN
County
Haywood
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
Covington - Alamo 161-kV TL
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- TVA
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.