TVA-519
50 MW generation in Marshall, MS · In queue since September 2022 · Proposed COD December 2029
50 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
7y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-14
TVA-519 is a proposed 50 MW solar generation project located in Marshall County, Mississippi. The project is listed in the Tennessee Valley Authority (TVA) interconnection queue with an entry date of September 2, 2022. Its proposed commercial operation date is December 14, 2029. The project's interconnection status is currently in the Facility Study phase.
The point of interconnection for TVA-519 is the Holly Springs - Chickasaw Trail IP 161-kV Transmission Line. The developer is listed as TVA. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
MS
County
Marshall
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
Holly Springs - Chickasaw Trail IP 161-kV TL
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TVA-519