TVA-522
67 MW generation in Choctaw, MS · In queue since September 2022 · Proposed COD May 2026
67 MW
Capacity
1
Components
Solar
3y 8m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
3y 8m
Schedule
0 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-05-01
TVA-522 is a proposed solar generation project with a total capacity of 67 MW, located in Choctaw County, Mississippi. The Tennessee Valley Authority (TVA) project entered the TVA interconnection queue on September 23, 2022, and has a proposed commercial operation date of May 1, 2026. Its interconnection point is the Red Hills - Leake 161-kV TL. The project's interconnection status is currently in the Facility Study phase.
The development project consists of 67 MW of solar photovoltaic generation. It is currently listed as an active project within the TVA interconnection queue.
Generated from interconnection queue and public data sources
State
MS
County
Choctaw
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
Red Hills - Leake 161-kV TL
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN