TVA-535
135 MW hybrid in Marshall, TN · In queue since March 2023 · Proposed COD May 2028
135 MW
Capacity
1
Components
Solar
3y 2m
In Queue
Facility Study
IA Status
COD target: 2028
Total Duration
5y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-05-30
TVA-535 is a proposed 135 MW hybrid solar and battery project located in Marshall County, Tennessee. The development project, which consists of 135 MW of solar capacity, is in the Tennessee Valley Authority (TVA) interconnection queue, with an entry date of March 22, 2023. Its proposed commercial operation date is May 30, 2028.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is TVA’s Franklin-Belfast 161-kV Transmission Line.
Generated from interconnection queue and public data sources
State
TN
County
Marshall
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
TVA_x0019_s Franklin-Belfast 161-kV Transmission Line
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- TVA
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TVA-535