TVA-538
150 MW hybrid in Henderson, TN · In queue since March 2023 · Proposed COD April 2029
150 MW
Capacity
1
Components
Solar
3y 2m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
6y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-04-24
TVA-538 is a proposed 150 MW hybrid solar and battery project in Henderson County, Tennessee. The development project consists of 150 MW of solar generation, coupled with battery storage. The project is located within the Tennessee Valley Authority (TVA) service area.
The project entered the TVA interconnection queue on March 28, 2023, with a proposed commercial operation date of April 24, 2029. Its interconnection agreement status is currently in the Facility Study phase. The point of interconnection is the Johnsonville Steam - Chesterfield 161-kV TL.
Generated from interconnection queue and public data sources
State
TN
County
Henderson
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
Johnsonville Steam - Chesterfield 161-kV TL
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- TVA
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TVA-538