TVA-540
150 MW generation in Chickasaw, MS · In queue since April 2023 · Proposed COD November 2029
150 MW
Capacity
1
Components
Solar
3y 1m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
6y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-11-13
TVA-540 is a proposed solar generation project with a total capacity of 150 MW, located in Chickasaw County, Mississippi. The project is listed in the Tennessee Valley Authority (TVA) interconnection queue, with an entry date of April 5, 2023. Its proposed commercial operation date is November 13, 2029. The project's interconnection status is currently in the Facility Study phase.
The development project consists of 150 MW of solar photovoltaic generation. The point of interconnection is the Okolona - Calhoun City 161kV Transmission Line.
Generated from interconnection queue and public data sources
State
MS
County
Chickasaw
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
Okolona - Calhoun City 161kV TL
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TVA-540