TVA-585
220 MW generation in Chickasaw, MS · In queue since September 2023 · Proposed COD May 2027
220 MW
Capacity
1
Components
Solar
2y 8m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-05-10
TVA-585 is a proposed solar generation project located in Chickasaw County, Mississippi. The project, with a total capacity of 220 MW, is being developed within the Tennessee Valley Authority (TVA) service area. It consists of 220 MW of solar photovoltaic generation.
The project entered the TVA interconnection queue on September 19, 2023, and has a proposed commercial operation date of May 10, 2027. Its interconnection status is currently in the Facility Study phase. The point of interconnection is TVA's Okolona - Calhoun City 161 kV transmission line.
Generated from interconnection queue and public data sources
State
MS
County
Chickasaw
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
TVA's Okolona - Calhoun City 161 kV TL
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TVA-585