TVA-586
20 MW storage in Wayne, TN · In queue since October 2023 · Proposed COD March 2029
20 MW
Capacity
1
Components
Battery
2y 7m
In Queue
Facility Study
IA Status
COD target: 2029
Total Duration
5y 5m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-03-01
TVA-586 is a proposed 20 MW battery storage project located in Wayne County, Tennessee. The project, under development by the Tennessee Valley Authority (TVA), entered the TVA interconnection queue on October 11, 2023, with a proposed commercial operation date of March 1, 2029. Its interconnection point is the Waynesboro City - Clifton City 69 kV transmission line. The project's interconnection status is currently in the Facility Study phase.
The proposed project consists solely of battery storage, with a total capacity of 20 MW. It is listed as an active project within the Tennessee Valley Authority's interconnection queue.
Generated from interconnection queue and public data sources
State
TN
County
Wayne
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
Waynesboro City - Clifton City 69 kV TL
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- TVA
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TVA-586