Project TVA-590 — Project Summary

Queue ID
TVA-590
Capacity
7 MW
Technology
Hydro
Status
active
Location
Marion, AL
Region
Southeast
Developer
IA Status
Cluster Study

TVA-590

TVA-590BetaActiveHydroTVALBNL

7 MW generation in Marion, AL · In queue since November 2023

7 MW

Capacity

1

Components

Hydro

2y 6m

In Queue

Cluster Study

IA Status

Interconnection

Total Duration

2y 6m

Impact Study25%
Queue EntryNov 3, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

About

TVA-590 is a proposed 7 MW hydroelectric generation project located in Marion County, Alabama. The project, developed by the Tennessee Valley Authority (TVA), entered the TVA interconnection queue on November 3, 2023. Its interconnection status is currently in the Cluster Study phase.

The proposed project's point of interconnection (POI) is at the Nickajack Dam.

Generated from interconnection queue and public data sources

Project Details

State

AL

County

Marion

Grid Region

Southeast

Market

Developer

Utility

Tennessee Valley Authority

Entity

TVA

Service Type

Point of Interconnection

Nickajack Dam

Data Source

LBNL

Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
Southern Company
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.