TVA-592
500 MW hybrid in Mississippi, AR · In queue since December 2023 · Proposed COD March 2027
500 MW
Capacity
1
Components
Solar
2y 5m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-03-15
TVA-592 is a proposed 500 MW hybrid solar and battery energy storage project located in Mississippi County, Arkansas. The development project, located in the Southeast region, consists of 500 MW of solar capacity. It is listed in the Tennessee Valley Authority (TVA) interconnection queue, with an entry date of December 1, 2023, and a proposed commercial operation date of March 15, 2027. The project's interconnection status is currently in the Facility Study phase.
The project is being managed within the TVA interconnection queue. TVA-592 is interconnected at the Shelby 500kV SS point of interconnection. The project has appeared in recent news coverage regarding TVA's renewable energy procurement plans.
Generated from interconnection queue and public data sources
State
AR
County
Mississippi
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
Shelby 500kV SS
Data Source
LBNL