TVA-618
800 MW generation in Stewart, TN · In queue since June 2024 · Proposed COD June 2027
800 MW
Capacity
1
Components
Gas
1y 11m
In Queue
Facility Study
IA Status
COD target: 2027
Total Duration
3 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-01
TVA-618 is a proposed 800 MW gas-fired generation project located in Stewart County, Tennessee. The project is being developed by the Tennessee Valley Authority (TVA) and interconnected to the Cumberland CC 500kV SS. It entered the TVA interconnection queue on June 12, 2024, with a proposed commercial operation date of June 1, 2027. The project's interconnection status is currently in the Facility Study phase.
The proposed project consists of 800 MW of gas-fired generation capacity. It is listed as an active project within the Tennessee Valley Authority's interconnection queue.
Generated from interconnection queue and public data sources
State
TN
County
Stewart
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
Cumberland CC 500kV SS
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- TVA
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.