TVA-620
1,600 MW generation in Trousdale, TN · In queue since June 2024 · Proposed COD June 2031
1,600 MW
Capacity
1
Components
Gas
1y 11m
In Queue
Cluster Study
IA Status
COD target: 2031
Total Duration
7 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2031-06-01
TVA-620 is a proposed 1600 MW gas-fired generation project located in Trousdale County, Tennessee. The project, developed by the Tennessee Valley Authority (TVA), entered the TVA interconnection queue on June 12, 2024, with a proposed commercial operation date of June 1, 2031. Its interconnection status is currently in the Cluster Study phase.
The proposed project has been the subject of recent news coverage.
Generated from interconnection queue and public data sources
State
TN
County
Trousdale
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
New Central Region Gas Plant
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- TVA
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-31