TVA-628
1,600 MW generation in Todd, KY · In queue since June 2024 · Proposed COD June 2030
1,600 MW
Capacity
1
Components
Gas
1y 11m
In Queue
Cluster Study
IA Status
COD target: 2030
Total Duration
6 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-06-01
TVA-628 is a proposed 1600 MW gas-fired generation project located in Todd County, Kentucky. The development project, under the entity TVA, entered the Tennessee Valley Authority (TVA) interconnection queue on June 12, 2024, with a proposed commercial operation date of June 1, 2030. Its interconnection status is currently in the Cluster Study phase.
The project's point of interconnection (POI) is the PARADISE - MONTGOMERY 500 KV line.
Generated from interconnection queue and public data sources
State
KY
County
Todd
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
PARADISE - MONTGOMERY 500 KV
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- TVA
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TVA-628