TVA-632
69 MW generation in Oktibbeha, MS · In queue since June 2024 · Proposed COD October 2028
69 MW
Capacity
1
Components
Solar
1y 11m
In Queue
Cluster Study
IA Status
COD target: 2028
Total Duration
4y 4m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-12
TVA-632 is a proposed solar generation project with a total capacity of 69 MW. The project is located in Oktibbeha County, Mississippi, within the service territory of the Tennessee Valley Authority (TVA). It entered the TVA interconnection queue on June 28, 2024, with a proposed commercial operation date of October 12, 2028.
The project's interconnection status is currently in the Cluster Study phase. The point of interconnection (POI) is the U Cement Tap - Holman MS 161 kV TL.
Generated from interconnection queue and public data sources
State
MS
County
Oktibbeha
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
U Cement Tap - Holman MS 161 kV TL
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.