TVA-639
100 MW generation in Jackson, AL · In queue since August 2024 · Proposed COD August 2029
100 MW
Capacity
1
Components
Solar
1y 9m
In Queue
Cluster Study
IA Status
COD target: 2029
Total Duration
5 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-08-01
TVA-639 is a proposed solar generation project with a total capacity of 100 MW, located in Jackson County, Alabama. The project is in the Tennessee Valley Authority (TVA) interconnection queue, with an entry date of August 28, 2024. Its proposed commercial operation date is August 1, 2029. The interconnection status is currently in the Cluster Study phase.
The point of interconnection (POI) is the Widow's Creek FP - Bellefonte NP 161kV TL. The developer is listed as TVA.
Generated from interconnection queue and public data sources
State
AL
County
Jackson
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
Widow_x0019_s Creek FP _x0013_ Bellefonte NP 161kv TL
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TVA-639