TVA-641
69 MW generation in Oktibbeha, MS · In queue since August 2024 · Proposed COD December 2028
69 MW
Capacity
1
Components
Solar
1y 9m
In Queue
Cluster Study
IA Status
COD target: 2028
Total Duration
4y 4m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
TVA-641 is a proposed solar generation project located in Oktibbeha County, Mississippi, with a total capacity of 69 MW. The project, under development by the Tennessee Valley Authority (TVA), consists of 69 MW of solar photovoltaic generation. It is currently listed as active in the Tennessee Valley Authority interconnection queue, with a queue entry date of August 29, 2024, and a proposed commercial operation date of December 1, 2028. The project's interconnection status is currently in the Cluster Study phase, and its point of interconnection is the TAP STR 97-LAFARGE HOLCIM (UNITED CEMENT) 161kV TL.
The proposed project is located in the Southeast region. Recent news coverage has discussed TVA's increasing activity in its interconnection queue.
Generated from interconnection queue and public data sources
State
MS
County
Oktibbeha
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
TAP STR 97-LAFARGE HOLCIM (UNITED CEMENT) 161kV TL
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TVA-641