Project TVA-642 — Project Summary

Queue ID
TVA-642
Capacity
96 MW
Technology
Solar
Status
active
Location
Muhlenberg, KY
Region
Southeast
Developer
IA Status
Cluster Study

TVA-642

TVA-642BetaActiveSolarTVALBNL

96 MW generation in Muhlenberg, KY · In queue since September 2024

96 MW

Capacity

1

Components

Solar

1y 8m

In Queue

Cluster Study

IA Status

Interconnection

Total Duration

1y 8m

Impact Study25%
Queue EntrySep 5, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

About

TVA-642 is a proposed 96 MW solar generation project located in Muhlenberg County, Kentucky. The project is sponsored by the Tennessee Valley Authority (TVA) and consists of 96 MW of solar photovoltaic generation.

The project is currently in the Tennessee Valley Authority interconnection queue, with an entry date of September 5, 2024. Its interconnection status is listed as "Cluster Study," and it is proposed to interconnect at TVA's Paradise CC 161-kV Substation.

Generated from interconnection queue and public data sources

Project Details

State

KY

County

Muhlenberg

Grid Region

Southeast

Market

Developer

Utility

Tennessee Valley Authority

Entity

TVA

Service Type

Point of Interconnection

TVA's Paradise CC 161-kV Substation

Data Source

LBNL

Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
TVA
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project TVA-642