Project TVA-655 — Project Summary

Queue ID
TVA-655
Capacity
24 MW
Technology
Hydro
Status
active
Location
Hamilton, TN
Region
Southeast
Developer
IA Status
Cluster Study

TVA-655

TVA-655BetaActiveHydroTVALBNL

24 MW generation in Hamilton, TN · In queue since September 2024 · Proposed COD February 2028

24 MW

Capacity

1

Components

Hydro

1y 8m

In Queue

Cluster Study

IA Status

COD target: 2028

Interconnection

Total Duration

3y 5m

Impact Study25%
Queue EntrySep 26, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-02-01

About

TVA-655 is a proposed 24 MW hydroelectric generation project located in Hamilton County, Tennessee. The project, under development by the Tennessee Valley Authority (TVA), entered the TVA interconnection queue on September 26, 2024, with a proposed commercial operation date of February 1, 2028. Its interconnection status is currently in the Cluster Study phase.

The project will interconnect at the Chickamauga HP Bus 360713. The project has appeared in recent news coverage regarding TVA's generation planning.

Generated from interconnection queue and public data sources

Project Details

State

TN

County

Hamilton

Grid Region

Southeast

Market

Developer

Utility

Tennessee Valley Authority

Entity

TVA

Service Type

Point of Interconnection

Chickamauga HP Bus 360713

Data Source

LBNL

Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
TVA
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.