TVA-656
54 MW generation in Benton, MS · In queue since October 2024 · Proposed COD February 2030
54 MW
Capacity
1
Components
Gas
1y 7m
In Queue
Cluster Study
IA Status
COD target: 2030
Total Duration
5y 4m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-02-01
TVA-656 is a proposed 54 MW gas-fired generation project located in Benton County, Mississippi. The project is listed in the Tennessee Valley Authority (TVA) interconnection queue with an entry date of October 1, 2024. Its proposed commercial operation date is February 1, 2030. The interconnection status is currently in the Cluster Study phase. The point of interconnection is the Magnolia CC Plant.
The proposed project, sponsored by TVA, has appeared in recent news coverage regarding TVA's generation planning.
Generated from interconnection queue and public data sources
State
MS
County
Benton
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
Magnolia CC Plant
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TVA-656