Project TVA-657 — Project Summary

Queue ID
TVA-657
Capacity
60 MW
Technology
Gas
Status
active
Location
Muhlenberg, KY
Region
Southeast
Developer
IA Status
Cluster Study

TVA-657

TVA-657BetaActiveGasTVALBNL

60 MW generation in Muhlenberg, KY · In queue since October 2024 · Proposed COD February 2030

60 MW

Capacity

1

Components

Gas

1y 7m

In Queue

Cluster Study

IA Status

COD target: 2030

Interconnection

Total Duration

5y 4m

Impact Study25%
Queue EntryOct 1, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-02-01

About

TVA-657 is a proposed 60 MW gas-fired generation project located in Muhlenberg County, Kentucky. The project is sponsored by the Tennessee Valley Authority (TVA) and has an interconnection queue entry date of October 1, 2024, in the TVA queue. Its proposed commercial operation date is February 1, 2030. The project's interconnection status is currently in the Cluster Study phase.

The proposed project is linked to the existing Paradise CC Plant and has appeared in recent news coverage regarding TVA's generation plans.

Generated from interconnection queue and public data sources

Project Details

State

KY

County

Muhlenberg

Grid Region

Southeast

Market

Developer

Utility

Tennessee Valley Authority

Entity

TVA

Service Type

Point of Interconnection

Paradise CC Plant

Data Source

LBNL

Market Context
Approximate
ISO / RTO
SOUTHEAST
Trading Hub
TVA
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project TVA-657