TVA-658
7 MW generation in Loudon, TN · In queue since October 2024
7 MW
Capacity
1
Components
Hydro
1y 7m
In Queue
Cluster Study
IA Status
Total Duration
1y 7m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
TVA-658 is a proposed 7 MW hydroelectric generation project located in Loudon County, Tennessee. The project, under development by the Tennessee Valley Authority (TVA), entered the TVA interconnection queue on October 1, 2024. Its point of interconnection is the Ft. Loudon Hydro Bus 364422.
The project's interconnection status is currently in the Cluster Study phase.
Generated from interconnection queue and public data sources
State
TN
County
Loudon
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
Ft. Loudon Hydro Bus 364422
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- TVA
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.