TVA-667
150 MW generation in Lawrence, AL · In queue since October 2024 · Proposed COD February 2026
150 MW
Capacity
1
Components
Solar
1y 7m
In Queue
Cluster Study
IA Status
COD target: 2026
Total Duration
1y 4m
Schedule
3 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-02-06
TVA-667 is a proposed solar generation project with a total capacity of 150 MW, located in Lawrence County, Alabama. The project is being developed within the Tennessee Valley Authority (TVA) service area. It entered the TVA interconnection queue on October 4, 2024, and has a proposed commercial operation date of February 6, 2026. The project's interconnection status is currently in the Cluster Study phase.
The proposed project consists of 150 MW of solar photovoltaic generation. The point of interconnection is the Wheeler-Trinty 161kV transmission line.
Generated from interconnection queue and public data sources
State
AL
County
Lawrence
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
Wheeler-Trinty 161kV TL
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN