TVA-672
140 MW generation in Rankin, MS · In queue since October 2024 · Proposed COD September 2027
140 MW
Capacity
1
Components
Solar
1y 7m
In Queue
Cluster Study
IA Status
COD target: 2027
Total Duration
2y 11m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-09-01
TVA-672 is a proposed 140 MW solar generation project located in Rankin County, Mississippi. The project is being developed within the Tennessee Valley Authority (TVA) service area. It entered the TVA interconnection queue on October 30, 2024, with a proposed commercial operation date of September 1, 2027.
The interconnection request is currently in the Cluster Study phase. The point of interconnection (POI) is TVA's Sebastopol-Leake 161kV transmission line.
Generated from interconnection queue and public data sources
State
MS
County
Rankin
Grid Region
Southeast
Market
—
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Service Type
—
Point of Interconnection
TVA's Sebastopol-Leake 161kV TL
Data Source
LBNL
- ISO / RTO
- SOUTHEAST
- Trading Hub
- Southern Company
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project TVA-672