WAPA-DSW-2018-G40
225 MW hybrid in Mohave, AZ · In queue since October 2018 · Proposed COD July 2020
225 MW
Capacity
1
Components
Solar
7y 7m
In Queue
—
IA Status
COD target: 2020
Total Duration
1y 9m
Schedule
71 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2020-07-01
The proposed WAPA-DSW-2018-G40 project is a 225 MW hybrid solar and battery energy storage development in Mohave County, Arizona. The project is located in the Western region and interconnects to the WAPA Desert Southwest Region via the Topock 230kV point of interconnection.
The project is currently listed as active in the WAPA-DSW interconnection queue, with an entry date of October 27, 2018. The proposed commercial operation date is July 1, 2020. The project consists of 225 MW of solar generation capacity.
Generated from interconnection queue and public data sources
State
AZ
County
Mohave
Grid Region
Mountain West
Market
—
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-DSW
Service Type
—
Point of Interconnection
Topock 230kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project WAPA-DSW-2018-G40