WAPA-DSW-2018-G41
225 MW hybrid in Mohave, AZ · In queue since October 2018 · Proposed COD July 2020
225 MW
Capacity
1
Components
Solar
7y 7m
In Queue
—
IA Status
COD target: 2020
Total Duration
1y 9m
Schedule
71 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2020-07-01
WAPA-DSW-2018-G41 is a proposed 225 MW hybrid solar and battery project located in Mohave County, Arizona. The project, under development within the Western Area Power Administration (WAPA) Desert Southwest Region, consists of 225 MW of solar capacity. It is interconnected to the WAPA-DSW queue as of October 27, 2018, with a proposed commercial operation date of July 1, 2020, at the Topock 230kV point of interconnection.
The project's interconnection status is listed as active. No interconnection agreement (IA) status is available. There is no match to an existing operating plant in the EIA database, and no recent news coverage is available.
Generated from interconnection queue and public data sources
State
AZ
County
Mohave
Grid Region
Mountain West
Market
—
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-DSW
Service Type
—
Point of Interconnection
Topock 230kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project WAPA-DSW-2018-G41