WAPA-DSW-2021-G2
22 MW hybrid in La Paz, AZ · In queue since March 2021 · Proposed COD December 2022
22 MW
Capacity
1
Components
Solar
5y 2m
In Queue
—
IA Status
COD target: 2022
Total Duration
1y 9m
Schedule
42 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-01
The proposed WAPA-DSW-2021-G2 project is a 22 MW hybrid solar and battery energy storage development in La Paz County, Arizona. The project is located in the Western region and interconnects to the WAPA Desert Southwest Region.
The project entered the WAPA-DSW interconnection queue on March 25, 2021, with a proposed commercial operation date of December 1, 2022. The project consists of 22 MW of solar generation capacity. The interconnection point of contact is the Harcuvar-Little Harquahala substation.
Generated from interconnection queue and public data sources
State
AZ
County
La Paz
Grid Region
Mountain West
Market
—
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-DSW
Service Type
—
Point of Interconnection
Harcuvar-Little Harquahala
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project WAPA-DSW-2021-G2