WAPA-DSW-2021-G4
462.5 MW hybrid in Pinal, AZ · In queue since April 2021 · Proposed COD July 2023
462.5 MW
Capacity
1
Components
Solar
5y 1m
In Queue
—
IA Status
COD target: 2023
Total Duration
2y 3m
Schedule
35 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-07-01
WAPA-DSW-2021-G4 is a proposed 462.5 MW hybrid solar and battery project located in Pinal County, Arizona. The development project consists of 462.5 MW of solar capacity. It is listed in the WAPA Desert Southwest Region interconnection queue as of April 28, 2021, with a proposed commercial operation date of July 1, 2023. The point of interconnection is the ED5 Substation.
The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
AZ
County
Pinal
Grid Region
Mountain West
Market
—
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-DSW
Service Type
—
Point of Interconnection
ED5 Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.