WAPA-DSW-2021-G6
135 MW generation in Yavapai, AZ · In queue since June 2021 · Proposed COD September 2025
135 MW
Capacity
1
Components
Wind
4y 11m
In Queue
—
IA Status
COD target: 2025
Total Duration
4y 3m
Schedule
7 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-09-30
WAPA-DSW-2021-G6 is a proposed 135 MW wind energy project located in Yavapai County, Arizona. The project is listed in the WAPA Desert Southwest Region interconnection queue, with an entry date of June 18, 2021. The proposed commercial operation date is September 30, 2025.
The project is currently listed as active in the interconnection queue. The point of interconnection is the Round Valley _x0013_ Prescott 230-kV Line.
Generated from interconnection queue and public data sources
State
AZ
County
Yavapai
Grid Region
Mountain West
Market
—
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-DSW
Service Type
—
Point of Interconnection
Round Valley _x0013_ Prescott 230-kV Line
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project WAPA-DSW-2021-G6