Project WAPA-DSW-2021-G6 — Project Summary

Queue ID
WAPA-DSW-2021-G6
Capacity
135 MW
Technology
Wind
Status
active
Location
Yavapai, AZ
Region
West
Developer
IA Status

WAPA-DSW-2021-G6

WAPA-DSW-2021-G6BetaActiveWindWAPA-DSWLBNL

135 MW generation in Yavapai, AZ · In queue since June 2021 · Proposed COD September 2025

135 MW

Capacity

1

Components

Wind

4y 11m

In Queue

IA Status

COD target: 2025

Interconnection

Total Duration

4y 3m

Schedule

7 months past proposed COD

Pre-Study0%
Queue EntryJun 18, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-09-30

About

WAPA-DSW-2021-G6 is a proposed 135 MW wind energy project located in Yavapai County, Arizona. The project is listed in the WAPA Desert Southwest Region interconnection queue, with an entry date of June 18, 2021. The proposed commercial operation date is September 30, 2025.

The project is currently listed as active in the interconnection queue. The point of interconnection is the Round Valley _x0013_ Prescott 230-kV Line.

Generated from interconnection queue and public data sources

Project Details

State

AZ

County

Yavapai

Grid Region

Mountain West

Market

Developer

Utility

WAPA Desert Southwest Region

Entity

WAPA-DSW

Service Type

Point of Interconnection

Round Valley _x0013_ Prescott 230-kV Line

Data Source

LBNL

Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
PALOVERDE
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project WAPA-DSW-2021-G6