WAPA-DSW-2022-G10
150 MW hybrid in Pinal, AZ · In queue since July 2022 · Proposed COD November 2025
150 MW
Capacity
1
Components
Solar
3y 10m
In Queue
—
IA Status
COD target: 2025
Total Duration
3y 4m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-11-20
The proposed WAPA-DSW-2022-G10 project is a 150 MW hybrid solar and battery energy storage development in Pinal County, Arizona. The project consists of 150 MW of solar photovoltaic generation. It is located in the West region and is being proposed within the WAPA Desert Southwest Region interconnection queue, with a point of interconnection at the ED5 Substation.
The project entered the WAPA-DSW queue on July 8, 2022, and has a proposed commercial operation date of November 20, 2025. The project's status is currently listed as active.
Generated from interconnection queue and public data sources
State
AZ
County
Pinal
Grid Region
Mountain West
Market
—
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-DSW
Service Type
—
Point of Interconnection
ED5 Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.