WAPA-DSW-2022-G11
350 MW hybrid in Maricopa, AZ · In queue since August 2022 · Proposed COD June 2025
350 MW
Capacity
1
Components
Solar
3y 9m
In Queue
—
IA Status
COD target: 2025
Total Duration
2y 10m
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-06-01
WAPA-DSW-2022-G11 is a proposed 350 MW hybrid solar and battery project located in Maricopa County, Arizona. The development project consists of 350 MW of solar capacity. It is in the WAPA Desert Southwest Region interconnection queue, with an entry date of August 11, 2022, and a proposed commercial operation date of June 1, 2025. The point of interconnection is the Harcuvar 230kV Substation.
The project is currently listed as active in the interconnection queue. There is no information available regarding the developer, interconnection agreement status, or any news coverage related to this project.
Generated from interconnection queue and public data sources
State
AZ
County
Maricopa
Grid Region
Mountain West
Market
—
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-DSW
Service Type
—
Point of Interconnection
Harcuvar 230kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.