WAPA-DSW-2022-G12
380 MW hybrid in La Paz, AZ · In queue since November 2022 · Proposed COD May 2026
380 MW
Capacity
1
Components
Solar
3y 6m
In Queue
—
IA Status
COD target: 2026
Total Duration
3y 6m
Schedule
0 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-05-01
WAPA-DSW-2022-G12 is a proposed 380 MW hybrid solar and battery project in La Paz County, Arizona. The development project, located in the West region, is listed in the WAPA Desert Southwest Region interconnection queue as of November 17, 2022. The proposed commercial operation date is May 1, 2026, and the point of interconnection is the Eagle Eye Substation 230kV.
The project consists of 380 MW of solar generation capacity. It is currently listed as active in the interconnection queue. Recent news coverage has discussed the project's potential impact on the region's energy infrastructure.
Generated from interconnection queue and public data sources
State
AZ
County
La Paz
Grid Region
Mountain West
Market
—
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-DSW
Service Type
—
Point of Interconnection
Eagle Eye Substation 230kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.