WAPA-DSW-2022-G5
225 MW hybrid in Mohave, AZ · In queue since April 2022 · Proposed COD December 2025
225 MW
Capacity
1
Components
Solar
4y 1m
In Queue
—
IA Status
COD target: 2025
Total Duration
3y 8m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-01
The proposed WAPA-DSW-2022-G5 project is a 225 MW hybrid solar and battery energy storage development project located in Mohave County, Arizona. The project consists of 225 MW of solar generation capacity. It is in the Western Area Power Administration (WAPA) Desert Southwest Region interconnection queue, with an entry date of April 27, 2022. The proposed commercial operation date is December 1, 2025, and the point of interconnection is the White Hills 345-kV Substation.
The project's interconnection status is listed as active. The developer is not specified in the queue data. Recent news coverage of the project is not indicated in the available data.
Generated from interconnection queue and public data sources
State
AZ
County
Mohave
Grid Region
Mountain West
Market
—
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-DSW
Service Type
—
Point of Interconnection
White Hills 345- kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN