WAPA-DSW-2022-G7
250 MW hybrid in Maricopa, AZ · In queue since June 2022 · Proposed COD June 2025
250 MW
Capacity
1
Components
Solar
3y 11m
In Queue
—
IA Status
COD target: 2025
Total Duration
3 years
Schedule
11 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-06-01
The proposed WAPA-DSW-2022-G7 project is a 250 MW hybrid solar and battery energy storage development project located in Maricopa County, Arizona. The project consists of 250 MW of solar generation. It is interconnected to the WAPA Desert Southwest Region, with a queue entry date of June 6, 2022, and a proposed commercial operation date of June 1, 2025. The point of interconnection is the Harcuvar 230kV Substation.
The project is currently listed as active in the WAPA-DSW interconnection queue.
Generated from interconnection queue and public data sources
State
AZ
County
Maricopa
Grid Region
Mountain West
Market
—
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-DSW
Service Type
—
Point of Interconnection
Harcuvar 230kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project WAPA-DSW-2022-G7