WAPA-DSW-2023-G1
270 MW hybrid in Pinal, AZ · In queue since January 2023 · Proposed COD January 2026
270 MW
Capacity
1
Components
Solar
3y 4m
In Queue
—
IA Status
COD target: 2026
Total Duration
3 years
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-01-09
WAPA-DSW-2023-G1 is a proposed 270 MW hybrid solar and battery project in Pinal County, Arizona. The project, located in the Western region, consists of 270 MW of solar capacity. It is listed in the WAPA Desert Southwest Region interconnection queue as of January 5, 2023, with a proposed commercial operation date of January 9, 2026.
The project is currently listed as active in the interconnection queue. The point of interconnection is the ED5 Substation.
Generated from interconnection queue and public data sources
State
AZ
County
Pinal
Grid Region
Mountain West
Market
—
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-DSW
Service Type
—
Point of Interconnection
ED5 Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project WAPA-DSW-2023-G1