WAPA-DSW-2023-G12
25 MW hybrid in Mohave, AZ · In queue since September 2023 · Proposed COD December 2026
25 MW
Capacity
1
Components
Solar
2y 8m
In Queue
—
IA Status
COD target: 2026
Total Duration
3y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-01
WAPA-DSW-2023-G12 is a proposed 25 MW hybrid solar and battery project located in Mohave County, Arizona. The development project consists of 25 MW of solar capacity. It is listed in the WAPA Desert Southwest Region interconnection queue, with an entry date of September 5, 2023.
The proposed commercial operation date for WAPA-DSW-2023-G12 is December 1, 2026. The point of interconnection is the Griffith Switchyard 230kV. The project's interconnection status is currently active.
Generated from interconnection queue and public data sources
State
AZ
County
Mohave
Grid Region
Mountain West
Market
—
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-DSW
Service Type
—
Point of Interconnection
Griffith Switchyard 230kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project WAPA-DSW-2023-G12