WAPA-DSW-2023-G14
250 MW hybrid in Pinal, AZ · In queue since October 2023 · Proposed COD March 2027
250 MW
Capacity
1
Components
Solar
2y 7m
In Queue
—
IA Status
COD target: 2027
Total Duration
3y 5m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-03-01
The proposed WAPA-DSW-2023-G14 project is a 250 MW hybrid solar and battery energy storage development in Pinal County, Arizona. The project consists of 250 MW of solar photovoltaic generation.
The project is actively listed in the WAPA Desert Southwest Region interconnection queue as of October 27, 2023, with a proposed commercial operation date of March 1, 2027. The point of interconnection is the ED5 230kV Substation.
Generated from interconnection queue and public data sources
State
AZ
County
Pinal
Grid Region
Mountain West
Market
—
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-DSW
Service Type
—
Point of Interconnection
ED5 230kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project WAPA-DSW-2023-G14