WAPA-DSW-2023-G17
300 MW hybrid in Mohave, AZ · In queue since December 2023 · Proposed COD December 2027
300 MW
Capacity
1
Components
Solar
2y 5m
In Queue
—
IA Status
COD target: 2027
Total Duration
4 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
The proposed WAPA-DSW-2023-G17 project is a 300 MW hybrid solar and battery energy storage system located in Mohave County, Arizona. The project consists of 300 MW of solar photovoltaic generation. It is in the West Area Power Administration (WAPA) Desert Southwest Region interconnection queue, with an entry date of December 20, 2023.
The proposed commercial operation date for the project is December 31, 2027. The point of interconnection is the Peacock 345kV Substation. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
AZ
County
Mohave
Grid Region
Mountain West
Market
—
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-DSW
Service Type
—
Point of Interconnection
Peacock 345kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project WAPA-DSW-2023-G17