WAPA-DSW-2023-G2
90 MW generation in Pinal, AZ · In queue since January 2023 · Proposed COD May 2024
90 MW
Capacity
1
Components
Gas
3y 4m
In Queue
—
IA Status
COD target: 2024
Total Duration
1y 4m
Schedule
24 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-05-01
WAPA-DSW-2023-G2 is a proposed 90 MW gas-fired generation project located in Pinal County, Arizona. The project is in the West region and is being developed within the WAPA Desert Southwest Region interconnection queue. The project consists of a single 90 MW gas component.
The project entered the WAPA-DSW queue on January 12, 2023, and has a proposed commercial operation date of May 1, 2024. The project's interconnection point of interconnection is the Coolidge _x0013_ Sundance 230kV line. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
AZ
County
Pinal
Grid Region
Mountain West
Market
—
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-DSW
Service Type
—
Point of Interconnection
Coolidge _x0013_ Sundance 230kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.