WAPA-DSW-2023-G5
225 MW hybrid in Mohave, AZ · In queue since April 2023 · Proposed COD December 2026
225 MW
Capacity
1
Components
Solar
3y 1m
In Queue
—
IA Status
COD target: 2026
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-30
WAPA-DSW-2023-G5 is a proposed 225 MW hybrid solar and battery project located in Mohave County, Arizona. The project consists of 225 MW of solar generation. It is listed in the WAPA Desert Southwest Region interconnection queue as of April 24, 2023, with a proposed commercial operation date of December 30, 2026.
The project is actively listed in the interconnection queue of WAPA-DSW. The point of interconnection is the White Hills 345-kV Substation.
Generated from interconnection queue and public data sources
State
AZ
County
Mohave
Grid Region
Mountain West
Market
—
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-DSW
Service Type
—
Point of Interconnection
White Hills 345- kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project WAPA-DSW-2023-G5