WAPA-DSW-2023-G6
150 MW hybrid in Mohave, AZ · In queue since May 2023 · Proposed COD January 2027
150 MW
Capacity
1
Components
Solar
3 years
In Queue
—
IA Status
COD target: 2027
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-01-15
WAPA-DSW-2023-G6 is a proposed 150 MW hybrid solar and battery project located in Mohave County, Arizona. The project, which consists of 150 MW of solar capacity, is in the WAPA Desert Southwest Region interconnection queue, with an entry date of May 2, 2023. The proposed commercial operation date is January 15, 2027.
The project is interconnected at the White Hills _x0013_ Peacock 345kV point of interconnection. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
AZ
County
Mohave
Grid Region
Mountain West
Market
—
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-DSW
Service Type
—
Point of Interconnection
White Hills _x0013_ Peacock 345kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project WAPA-DSW-2023-G6