WAPA-DSW-2023-G8
250 MW hybrid in La Paz, AZ · In queue since July 2023 · Proposed COD April 2027
250 MW
Capacity
1
Components
Solar
2y 10m
In Queue
—
IA Status
COD target: 2027
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-04-01
The proposed WAPA-DSW-2023-G8 project is a 250 MW hybrid solar and battery energy storage development in La Paz County, Arizona. The project, located in the West region, consists of 250 MW of solar generation. It is being proposed within the Western Area Power Administration (WAPA) Desert Southwest Region interconnection queue, with an entry date of July 10, 2023. The proposed commercial operation date is April 1, 2027, and the point of interconnection is the Bouse 230kV Substation.
The project is currently listed as active in the interconnection queue. No information is available regarding an executed Interconnection Agreement or news coverage of the project.
Generated from interconnection queue and public data sources
State
AZ
County
La Paz
Grid Region
Mountain West
Market
—
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-DSW
Service Type
—
Point of Interconnection
Bouse 230kV Substation
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project WAPA-DSW-2023-G8