WAPA-DSW-2024-G2
200 MW generation in Mohave, AZ · In queue since February 2024 · Proposed COD October 2027
200 MW
Capacity
1
Components
Gas
2y 3m
In Queue
—
IA Status
COD target: 2027
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-10-15
WAPA-DSW-2024-G2 is a proposed 200 MW gas-fired generation project located in Mohave County, Arizona, within the Western Electricity Coordinating Council (WECC) region. The project is being proposed within the Western Area Power Administration (WAPA) Desert Southwest Region interconnection queue, under the queue ID WAPA-DSW-2024-G2. The queue entry date is February 7, 2024, with a proposed commercial operation date of October 15, 2027. The point of interconnection is the Griffith Switchyard 230kV.
The proposed project consists of 200 MW of gas-fired generation capacity. As of the current data, the project's interconnection agreement (IA) status is not available. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
AZ
County
Mohave
Grid Region
Mountain West
Market
—
Developer
—
Utility
WAPA Desert Southwest Region
Entity
WAPA-DSW
Service Type
—
Point of Interconnection
Griffith Switchyard 230kV
Data Source
LBNL
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- PALOVERDE
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.